Choose what to fund. Make the trade-offs clear.

A ranked list of projects is not yet an allocation. Management still needs to know which combination to fund, whether it fits the budget and what the organisation is choosing to leave undone.

The complication is that projects rarely operate independently. They can serve the same customers, depend on one another or compete for the same staff. Some only work above a minimum funding level. Others create costs that continue after the initial budget ends.

A resource-allocation framework should make those interactions visible. Start with the outcome, then build a feasible portfolio around it.

Agree on what the money is meant to achieve

Suppose a city has $40 million over three years to improve access to jobs. It is considering more frequent buses, fare support and new feeder routes.

“Improve transport” is too broad to compare those options. In this case, define the main measure as additional residents able to reach a relevant employment centre within 45 minutes, at the times they need to travel and at an affordable fare. The city also has minimum access obligations for low-income riders.

That definition changes the analysis. Cheaper tickets do little for someone whose bus does not run before their shift. A new route may not help if an unreliable connection pushes the total journey beyond 45 minutes.

Ask how the outcome will be measured and which obligations are non-negotiable. A project with a high average benefit cannot compensate for failing a required service condition unless the decision-maker explicitly changes that condition.

Put every proposal on the same budget basis

Use the same three-year period for costs and benefits. Clarify whether the $40 million covers operating spending only, whether vehicles and infrastructure are already available, and what funding is committed beyond the period.

For this example, assume all figures below include the additional operating costs over three years and that required vehicles are available. Do not compare one route's annual cost with another route's three-year commitment.

Also check delivery capacity. A programme can fit the cash budget while exceeding the supply of drivers, maintenance staff or available depot space. Record those requirements alongside each proposal before adding projects together.

This is the public-service version of the constraint check in a growth strategy: an attractive opportunity is useful only if the organisation can deliver it.

Compare additional reach, then inspect the explanation

Suppose the proposals have these estimates relative to the existing service:

ProposalThree-year costAdditional residents with access if delivered alone
More frequent service on key corridors$20m20,000
Broad fare discounts$10m4,000
A feeder route$12m10,000

The frequency proposal reaches 1,000 additional residents per $1 million. Broad fare discounts reach 400. The feeder route reaches about 833 when considered alone.

Those ratios provide a first comparison. They do not tell you to allocate every available dollar to frequency. The $20 million proposal may cover all suitable corridors at that service level; the next dollar may earn much less. The feeder route may also reach a population with an access requirement that the corridors do not serve.

HM Treasury's Green Book treats the preferred option as a judgment across objectives, costs, benefits, risks and distributional effects. A single ranking is not the whole decision.

Remove overlap and test dependencies

Suppose 4,000 of the feeder route's 10,000 residents are already counted in the frequency proposal. Funding both adds 26,000 unique residents, not 30,000.

The feeder therefore adds 6,000 residents to that combination, making its incremental reach 500 per $1 million once the corridor programme is selected. That remains above the broad fare proposal's standalone ratio, but it is lower than the feeder's initial 833.

Now ask whether the estimates capture connections correctly. Some residents may gain useful access only when both a feeder and a more frequent main route operate. That is an interaction to model, not a reason to subtract all shared passengers automatically.

Define the unit carefully. A person benefiting from both projects can experience two improvements, but should be counted once in a measure of unique residents newly achieving the access threshold. If the objective instead includes total travel-time savings, their additional time benefit may still matter.

Quick Case Math Drill

A broadband provider has approved a fibre extension across a rural county and is deciding whether a fixed-wireless mast is still worth funding.

Mast coverage
8,000 homes
Also covered by fibre
3,000 of those homes
Mast cost
£2.5 million

How many newly reached homes does the mast add per £1 million?

Respect minimum viable commitments

Assume the feeder needs the full $12 million to run at a useful frequency over the three years. Giving it $6 million does not necessarily deliver half of the access benefit. It may create a service too infrequent to connect with work shifts.

Compare a properly designed smaller version if one exists, with its own costs and outcomes. Do not invent proportional benefits to make the budget fit.

The same issue appears in commercial cases. Half-funding a product integration may leave the product unusable; adding one employee to a team that needs three specialists may not unlock the project. Dependencies and minimum commitments belong in the allocation itself.

Show the complete portfolio

Suppose targeted fare support costing $4 million is needed to meet the city's stated access obligation. A feasible initial proposal is:

AllocationAmount
Corridor frequency$20m
Feeder route$12m
Targeted fare support$4m
Reserve for specified delivery uncertainty$4m
Total$40m

The broad fare discount remains unfunded. Explain why: it adds less reach per dollar under the initial estimates and is less targeted than the support required by the access obligation.

Frequency and the feeder provide an estimated 26,000 unique additional residents with access. Do not add a further reach number for the targeted support until you know whom it serves and how it interacts with those residents. It may make the assumed access affordable rather than adding an entirely separate group.

The reserve also needs a purpose. Identify the costs or uncertainties it covers, who can release it and what evidence would justify spending it. Keeping money unallocated is sensible only when it improves the overall decision compared with the best available use today.

Quick Prioritisation Drill

A hotel group is setting next year's capital plan and wants the feasible portfolio that adds the most annual operating profit.

Capital budget
£32m after contingency
Fire-safety upgrade
£8m, legally required
Project scope
Each project is all or nothing
ProjectCostAdded annual profit
Room refurbishment£20m£5.0m
Conference wing£12m£2.7m
Spa£12m£2.5m

Which projects should the group fund alongside the fire-safety upgrade?

Choose your answer

Stress-test the recommendation

If driver costs rise, does the portfolio still fund the promised service for all three years? If the feeder reaches only half the expected additional residents, would another option become preferable? If the access gap is mainly outside the selected corridors, does the portfolio still meet the objective?

These are practical sensitivities. Start with the assumptions most likely to change the choice, rather than varying every number by an arbitrary percentage.

Also ask what happens in year four. A three-year grant can fund a trial, but it cannot support a permanent service promise without a continuation plan. Compare recurring commitments with the realistic funding available after the grant.

Make reallocation possible without undermining delivery

Set a review point and measures tied to the objective: actual journey times, reliable access at relevant hours, affordability for priority groups and total delivery cost. Ridership helps explain demand, but a full bus alone does not demonstrate that the previously underserved population can reach work.

If evidence differs from the forecast, assess whether the cause is poor implementation or a weak premise. Fixing an unreliable connection is different from abandoning a route with no meaningful demand.

Let the desired outcome guide resource choices and the evidence you collect afterwards. Our public-sector framework develops the outcome question further.

For a commercial version, try Bank Branch Rationalization. Explain which locations to retain or change, including overlapping coverage, customer access and costs that genuinely disappear.

Structure drill

Would your case structure convince an MBB interviewer?

Bank Branch Rationalization

Compare branch-level economics and access needs before choosing which bank locations to close. Present your approach to Casey, Case Room’s AI interviewer, then review feedback on your structure and starting point.

Frequently asked questions

Setting up a fair comparison

How do I define the objective when the brief is vague?

Turn the broad aim into a single measure that every option can be judged against. “Improve transport” is too broad to compare more frequent buses, fare support and new feeder routes. The guide's city example uses additional residents able to reach a relevant employment centre within 45 minutes, at the times they need to travel.

What if proposals quote costs over different time periods?

Convert them to one basis before comparing anything. Use the same three-year period for both costs and benefits, and never set one route's annual cost against another's three-year cost. Also clarify whether the budget covers operating spending only and whether vehicles or infrastructure are already available.

What about costs that continue after the budget period ends?

Ask what funding is committed beyond the period before you allocate. Some projects create costs that continue after the initial budget ends, so a portfolio that fits the three years may leave an unfunded obligation afterwards. Clarifying this early stops you recommending services the organisation cannot sustain.

Comparing and combining options

Which project gives the best value for money?

Start with additional outcome per $1 million, then question the estimate behind it. On standalone figures, corridor frequency reaches 1,000 residents per $1 million, the feeder route about 833 and broad fare discounts 400. A strong ratio is only as good as its explanation, so check how each reach estimate was produced.

How do I deal with projects that serve the same people?

Count unique beneficiaries, not the sum of standalone estimates. If 4,000 of the feeder route's 10,000 residents are already reached by the frequency programme, funding both adds 26,000, not 30,000. The feeder's incremental reach falls to 6,000, or 500 per $1 million, still above broad fare discounts but below its standalone figure.

Do I need to check whether projects rely on each other?

Yes. Projects can depend on one another or compete for the same staff, so a combination that fits the budget may still be undeliverable. Check whether each option needs another to work, and whether shared capacity can support everything you select, before treating the portfolio as final.

Can I fund half a project to get half the benefit?

Usually not. The feeder needs its full $12 million to run at a useful frequency, and $6 million might produce a service too infrequent to connect with work shifts. If a properly designed smaller version exists, assess it with its own costs and outcomes rather than assuming benefits scale proportionally.

Finalising and adjusting the portfolio

How is an allocation different from a ranked list of projects?

A ranked list does not tell management which combination to fund, whether it fits the budget or what is being left undone. An allocation does. The city example assigns the full $40 million across corridor frequency, the feeder route, targeted fare support and a reserve, so the trade-offs are visible.

Should obligations be funded even if they are not the best value?

Yes, if they are genuine requirements. In the example, targeted fare support costing $4 million is assumed to be needed to meet the city's stated access obligation, so it enters the portfolio regardless of its ratio. Separate binding requirements from preferences before ranking the discretionary options.

Why hold a reserve instead of funding another project?

The guide's portfolio holds $4 million for specified delivery uncertainty. The word specified matters: a reserve should be linked to identifiable delivery risks, such as cost increases, rather than serve as an unexplained cushion. That makes it easier to defend when the interviewer asks why the money is not spent on outcomes.

How should I stress-test my allocation?

Start with the assumptions most likely to change the choice. Ask whether rising driver costs would still let the portfolio fund the promised service for all three years, whether the feeder reaching only half its expected residents would make another option preferable, and whether the access gap lies mainly outside the selected corridors.

Is ridership a good way to measure success?

Only partly. Ridership helps explain demand, but a full bus does not prove the previously underserved population can reach work. Track measures tied to the objective instead: actual journey times, reliable access at relevant hours, affordability for priority groups and total delivery cost.

If results disappoint, should the money be moved elsewhere?

Diagnose the cause before moving anything. Assess whether the shortfall comes from poor implementation or a weak premise. An implementation problem may be fixable within the existing project, whereas a flawed premise may justify reallocation. Agreeing a review point in advance makes that decision possible without disrupting projects that are working.