Compare the routes to usable capacity.

The cheapest way to add capacity can be the wrong answer if it delivers too little, arrives late or cannot serve the customer's workloads.

That is the central judgment in a data centre expansion case. A build-versus-lease table becomes useful only after both options meet the same requirement. Until then, you may be comparing two different products.

Here is how I would take the case from the opening structure to a recommendation, including the information that can overturn the first financial answer.

The case: deliver 12 MW within two years

A data centre operator needs an additional 12 megawatts of usable IT capacity within two years. It can expand an existing site or lease capacity from a partner. Both routes must meet the customer's availability and data-location requirements.

The client wants the better five-year cash outcome and can commit no more than £30 million upfront. Customer IT hardware is outside this comparison and is funded separately under either route.

The important words are usable IT capacity. A site's total electricity supply also supports cooling and other facility equipment. A 12 MW electricity connection does not automatically mean 12 MW is available for customer IT.

Confirm the capacity definition, when the customer needs it and whether 12 MW must be available together or can arrive in phases. Those answers determine which options are feasible.

Build the structure around three tests

I would present the opening in this order:

“First, I would check which routes can provide the full 12 MW by the deadline and meet the service requirements. Second, I would compare their cash flows over the same five-year period, including upfront investment and ongoing costs. Third, I would test the risks most likely to change that answer, particularly power availability, construction timing and the partner's committed capacity.”

This order prevents detailed financial work on an option that fails a non-negotiable requirement.

TestQuestions that matter
Deliver the required serviceHow much usable IT capacity, at which location, on what date, with what availability?
Compare the economicsWhat cash leaves upfront, what cash comes in during operation, and what remains at the end?
Test the weak assumptionsWhich permissions, connections, equipment or partner commitments could change cost or timing?

Check grid connections and electrical equipment as specific sources of delay. A named dependency is more useful than a vague bullet labelled “implementation risk.”

Quick Structuring Drill

A frozen-food distributor must add 20,000 pallet spaces of cold storage by April. It can build its own store or lease from a logistics firm.

Sort each question into the opening test where it belongs.

Put both options on the same clock

The interviewer supplies a simplified cash exhibit. These are case figures, not construction-cost benchmarks.

Both options are initially assumed to deliver the full 12 MW on the promised date. The comparison covers the five years beginning on that date. Assume full customer occupancy throughout, no price changes and no residual value at the end. Ongoing costs include the facility costs in scope; customer IT costs are excluded from both options.

Cash itemBuildLease
Upfront investment£28m£2m
Annual customer receipts£15m£15m
Annual operating payments£4m£10m
Annual operating cash£11m£5m

Over the stated window:

  • Build: 5 × £11m − £28m = £27m.
  • Lease: 5 × £5m − £2m = £23m.

Build leads by £4 million and fits the £30 million upfront limit. It consumes £26 million more upfront than leasing, then produces £6 million more operating cash each year.

Those differences explain the trade-off. The client pays more initially to keep more of the operating economics later.

This exhibit gives an undiscounted cash comparison. If the client asks for an investment valuation, request the discount rate, actual payment dates and end-of-period asset or contractual value. Do not quietly relabel £27 million as net present value.

Test what a delay does to that answer

Now the interviewer reveals that the build could open six months late. The lease remains available on time.

The five-year comparison window stays fixed. For this sensitivity, assume building costs remain £28 million, operating receipts and costs start together when the site opens, and there are no delay penalties. The delayed build has only 4.5 operating years in the window:

4.5 × £11m − £28m = £21.5m.

Lease still produces £23 million. The financial preference reverses even before any additional construction costs or customer penalties.

The original £4 million advantage buys only £4m ÷ £11m = 0.364 operating years, roughly 4.4 months, of delay under these assumptions.

That is a useful sensitivity to say aloud. It turns “construction timing matters” into a threshold the client can investigate.

But do not let the calculation obscure the deadline. If the customer cannot accept a late opening, the delayed build fails the service requirement regardless of its eventual cash return. You would need an on-time alternative or a credible bridging arrangement.

Quick Structuring Drill

A parcel carrier is choosing between building and leasing a sorting hub over a fixed five-year window. A build delay would not change its cost or trigger penalties.

Build five-year cash
£27m after upfront cost
Lease five-year cash
£24m, ready on time
Build cash once open
£9m a year

Which recommendation should you state, given the build may open late?

Choose your answer

A cheaper 8 MW offer does not solve a 12 MW requirement

Suppose the partner then confirms that only 8 MW is firmly available by the deadline. The remaining 4 MW is an option without a committed delivery date.

You now have a new feasibility problem. An 8 MW lease cannot inherit the £15 million receipts assumed for a fully occupied 12 MW facility. Nor can you compare its lower price with the full build price and declare leasing cheaper.

Ask for a firm 12 MW offer or construct a complete alternative: 8 MW with this partner plus 4 MW elsewhere, including any extra connectivity, coordination and service costs. Check whether splitting the workload across locations is acceptable to the customer.

The correct response is to update the comparison. You do not need to defend the earlier answer after an assumption changes.

Separate efficiency from capacity

Power efficiency can affect operating costs, but it does not replace a capacity check.

PUE is the ratio of total facility power to IT power. It describes facility overhead, but does not by itself establish the usable IT capacity the site can guarantee under its operating conditions.

For the interview, ask what capacity the engineering team will commit to, what connection supports it and what electricity cost assumptions are in the exhibit. You can follow the commercial implications without pretending to size the facility yourself.

Finish with the decision and its conditions

On the initial numbers, the answer is:

“Build provides £4 million more cash over the five-year window and stays within the upfront limit. I would choose it if the full 12 MW can be delivered on time. The advantage disappears after roughly four months of delay, so the next priority is validating the power connection and construction schedule. If the deadline cannot be met, we need a firm lease or bridging option for the full requirement.”

That recommendation explains what you prefer, why, and what could change it.

Practise the same comparison in the manufacturing capacity structure drill. For the broader entry decision, read the market-entry framework.

Structure drill

Would your case structure convince an MBB interviewer?

Manufacturing Capacity Bottleneck

Present your approach aloud. Get feedback on how you break down the problem, prioritise your analysis and explain your structure.

Frequently asked questions

Framing the requirement

Why not simply compare the build and lease prices?

Because a price comparison means something only once both options meet the same requirement. Each must deliver the full 12 MW of usable IT capacity within two years and meet availability and data-location needs. Otherwise you may be comparing two different products, and the cheaper one could arrive late or deliver too little.

What constraints must any option satisfy?

It must add 12 MW of usable IT capacity within two years, meet the customer's availability and data-location requirements, and need no more than £30 million upfront. Among options that pass, the client wants the better five-year cash outcome. Customer IT hardware sits outside this comparison.

How should I structure my opening?

Use three tests in order. First, check which routes can deliver the full 12 MW by the deadline and meet service requirements. Second, compare cash flows over the same five-year period, including upfront and ongoing costs. Third, test the risks most likely to change the answer, such as power availability and construction timing.

Comparing five-year cash

What does putting both options 'on the same clock' mean?

It means measuring both over the same five years, starting from the promised delivery date. The simplified exhibit assumes full occupancy, no price changes and no residual value at the end. Holding these constant means the gap reflects genuine differences between build and lease rather than mismatched timeframes.

On the initial numbers, which option wins?

Build wins, providing £4 million more cash over the five-year window. Its £28 million upfront cost also stays within the £30 million limit. However, that result assumes the build delivers the full 12 MW on the promised date, which is exactly what the risk test must examine next.

Should I treat the exhibit figures as realistic construction costs?

No. The interviewer presents them as simplified case figures, not construction-cost benchmarks. Use them to demonstrate the method: equal capacity, equal timeframe, and upfront investment plus ongoing costs. Bringing in your own industry assumptions unprompted can make your comparison inconsistent with the exhibit.

Delay risk and the recommendation

How much does a six-month delay change the answer?

Enough to reverse it. With the window fixed, the build operates for only 4.5 years: 4.5 × £11 million less £28 million gives £21.5 million. Losing half a year of operating cash wipes out the original £4 million lead, so the on-time lease becomes better, assuming no delay penalties.

How long can the build slip before the lease becomes the better choice?

Roughly four months. The build's £4 million advantage sits against about £11 million of operating cash a year, so each month of delay erodes nearly £1 million. That is why validating the power connection and construction schedule matters more than refining the cost estimates.

How should I phrase the final recommendation?

Lead with the decision, then state its conditions. For example: build provides £4 million more cash over five years within the upfront limit, so choose it if the full 12 MW can be delivered on time. Add that the advantage disappears after about four months of delay and explain what follows if the deadline cannot be met.

Capacity traps

If the partner offers 8 MW more cheaply, can I compare it with the build?

No. An 8 MW lease is a feasibility problem, not a cheaper version of the same option. It cannot inherit the £15 million receipts assumed for a fully occupied 12 MW facility, and its lower price cannot be set directly against the full build price.

How should I treat the remaining 4 MW offered as an option?

Treat it as unconfirmed, because it has no committed delivery date. It does not help meet the 12 MW deadline as things stand. Ask how and when the gap would be filled, then compare complete solutions that meet the requirement rather than crediting the option as if it were firm capacity.

Does a better PUE mean a site can deliver more capacity?

No. PUE is the ratio of total facility power to IT power, so it describes facility overhead and can affect operating costs. It does not by itself establish the usable IT capacity a site can guarantee. Ask what capacity the engineering team will commit to and what power connection supports it.